Building transmission lines across multiple states is one of the most complex challenges in modern energy infrastructure. The process requires securing hundreds, sometimes thousands, of property easements while navigating a maze of regulatory requirements that differ from one jurisdiction to the next. For companies working in transmission development like Almighty Energy, understanding these challenges isn’t just academic it’s the difference between projects that move forward and those that stall indefinitely.

The reality is stark. New transmission lines now take five to 20 years to develop, with projects initiated since 2005 taking over 10 years on average to complete. Much of this delay stems from the land aggregation process itself, where securing continuous rights-of-way across state boundaries presents both legal and practical obstacles that many developers underestimate.

Why Interstate Transmission Land Acquisition Is Different

Unlike power plants that require a single site in one state, transmission infrastructure cuts across property boundaries, municipal lines, and state borders. This fundamental difference creates unique challenges.

A short line that can use an existing right-of-way along a federal highway is easier to approve than an interregional line that crosses federal, state, and private lands in various locations. Once a line crosses multiple land types, the list of necessary approvals and potential challengers grows exponentially.

State-level differences compound the problem. Obtaining approvals in each state is often difficult because many states focus on intrastate burdens and benefits, so a transmission line that doesn’t directly connect resources within a state might not receive permits required to traverse that state. This creates a situation where states in the middle of a transmission corridor may block projects they perceive as benefiting their neighbors rather than their own residents.

The scale of these projects magnifies every challenge. Unlike other types of infrastructure like a bridge or power plant, transmission lines can stretch for hundreds of miles, requiring continuous land rights from start to finish. A single property owner’s refusal can jeopardize entire sections of a planned route.

The Right-of-Way Acquisition Process: What Actually Happens

The land acquisition process for transmission lines follows a general pattern, though specifics vary by state. Understanding this process is essential for any organization, including Almighty Energy, working to expand transmission infrastructure.

After regulatory approval, developers must secure easements from every property owner along the route. The appraisal process determines the current value of the property and the value with the transmission line on it the difference between the two is the value of the easement. This compensation is based on what the owner has lost, rather than the value to the utility.

Negotiation strategies matter. For transmission lines, developers sometimes have the flexibility to offer additional compensation to landowners to keep projects moving forward and on schedule. Beyond monetary adjustments, developers can offer non-monetary solutions, such as slightly adjusting the location of structures to lessen impacts on viewsheds, agriculture, or other land uses.

Great River Energy pays landowners whose property the line crosses a one-time easement payment, which varies based on the land involved. Some developers have experimented with alternative compensation structures, including annual per-pole payments that continue as long as structures remain on the property.

Navigating the Eminent Domain Question

When negotiations fail, utilities may turn to eminent domain. This power, granted by states to utilities, allows condemnation of land for facilities that benefit the general public. But the process isn’t simple or quick.

To be successful in an eminent domain process, the electric utility must first establish a need for the new facility, then show that in its route selection it has considered and evaluated costs, safety, long-range area planning, environmental factors, and alternative routes. Only after these showings can the utility exercise eminent domain.

Property owners have substantial protections. In Missouri, utilities must provide up to 60 days for landowners to seek advice before eminent domain court proceedings can start, and a written offer must be held open for at least 30 days before a court action can begin. Similar protections exist in other states, though they vary.

Compensation in these cases typically reflects the property’s loss in value. In partial taking cases, where the utility company needs only part of the owner’s property, the property owner’s compensation is usually calculated as the difference between the property’s value before and after the taking.

What many property owners don’t realize is that compensation often extends beyond the land directly taken. Damages to remaining property including visual impacts, noise, and restrictions on future use should factor into the calculation.

State-by-State Variations That Complicate Multi-State Projects

Each state has evolved its own approach to transmission siting decisions. Most states historically gave the task of approving the need for major transmission facilities and the choice of route to their utility regulatory agency the Public Service Commission, Public Utility Commission, Commerce Commission, or Corporation Commission. But the specific processes, timelines, and requirements differ dramatically.

These differences mean that multi-state transmission developers face fundamentally different rules as their projects cross state lines. A developer working on a project that crosses five states may need to satisfy five completely different regulatory frameworks, each with its own public participation requirements, environmental standards, and cost allocation methods.

Only a small fraction of projects undergo federal environmental review (3.5%), but these projects comprise 26% of all new line miles added to the bulk power system. This suggests that longer, multi-state projects face disproportionate challenges compared to shorter, intrastate lines.

The federal government has attempted to address these inconsistencies. The Department of Energy recently finalized rules for its Coordinated Interagency Transmission Authorizations and Permits (CITAP) program, which establishes DOE as the lead agency for NEPA reviews of qualifying high-powered nationally or regionally important lines, with a target review timeline of two years.

Landowner Relations: Where Projects Succeed or Fail

Community opposition can derail even technically sound projects. A transmission line is not merely a complex piece of infrastructure subject to complex decision-making, but also a public relations and community engagement challenge.

Real-world examples illustrate the stakes. The proposed Maryland Piedmont Reliability Project’s 70-mile route would threaten more than 4,000 acres of land, including farmland, forest, and protected wildlife habitats, facing harsh opposition from Marylanders who say their land is being used to benefit out-of-state interests.

Early engagement proves essential. Great River Energy has individuals very familiar with their service territory, with their communities, with local governmental units and state governmental units and agencies who work collaboratively to solve problems when they have to site projects. This local expertise and relationship-building can mean the difference between smooth negotiations and protracted conflicts.

Transparency about project benefits and impacts matters. When landowners feel developers are being straightforward about who benefits from a project and how their property will be affected, negotiations proceed more smoothly. When they suspect they’re being used as a pass-through for someone else’s benefit, resistance hardens.

Cost Allocation Disputes Across State Lines

One of the thorniest issues in multi-state transmission projects is determining who pays. Since a long-distance transmission line may cross multiple states, the analysis of who benefits and who should pay for such infrastructure is anything but straightforward, with the PUC of each state working to make sure their ratepayers are not unduly subsidizing projects whose benefits may accrue elsewhere.

This creates a collective action problem. States and utilities that would benefit most from a new transmission line have incentives to see it built, but states in the middle of the route may see mostly costs land use impacts, visual changes, and infrastructure maintenance without proportional benefits.

The system really flounders when a line would span a long distance, running across multiple states, with stakeholders looking at each other saying “Well, you pay for it. No, you pay for it”. This impasse has blocked numerous projects that might otherwise serve regional or national interests.

Recent federal actions have begun addressing cost allocation more systematically. FERC’s Order 1920 on transmission and cost allocation requires transmission providers to implement more consistent approaches to planning and paying for multi-state projects.

Lessons Learned: What Works in Multi-State Land Aggregation

After decades of experience building transmission lines, several best practices have emerged for companies like Almighty Energy working to aggregate land across state boundaries.

  1. Start early with stakeholder engagement. Waiting until after regulatory approval to contact landowners is a recipe for conflict. Successful developers begin conversations early, before routes are finalized, allowing property owners to voice concerns that might be addressed through route adjustments.
  2. Invest in local expertise. Having staff or contractors who know the territory, understand local concerns, and have existing relationships with communities can dramatically smooth the acquisition process. These relationships can’t be built overnight or parachuted in from corporate headquarters.
  3. Offer fair compensation from the start. Results vary by property and project, but clients who hire legal representation almost always receive far more compensation than they are initially offered. Starting with fair offers reduces conflict and legal costs down the line.
  4. Be flexible on route micro-adjustments. While the general corridor may be fixed, showing willingness to adjust tower locations or easement boundaries to minimize impacts on specific properties demonstrates good faith and can resolve impasses.
  5. Communicate transparently about project benefits. When a project primarily benefits out-of-state consumers, saying so upfront and compensating accordingly is better than appearing to hide the truth. Landowners appreciate honesty even when the news isn’t what they want to hear.
  6. Consider alternative compensation structures. One-time payments work for some landowners, but others might prefer annual payments, particularly for agricultural land where ongoing impacts affect year after year of farming operations.
  7. Document everything meticulously. With projects spanning years and multiple jurisdictions, clear documentation of agreements, communications, and commitments prevents misunderstandings that can lead to legal disputes later.

The Role of Federal Reform in Easing Multi-State Challenges

The difficulties of multi-state land aggregation have prompted calls for federal reform. The decentralized siting and permitting process for transmission lines causes significant project delays and cancellations, with primary federal siting authority potentially providing certainty to developers and supporting transmission expansion.

Some proposed solutions include creating Regional Siting Commissions that would allow groups of states to coordinate their permitting processes. RSCs could be paired with ISO/RTOs to provide a unified state voice for interstate transmission siting for states within or wishing to connect to ISO/RTO systems.

The Department of Energy’s designation of National Interest Electric Transmission Corridors (NIETCs) represents another federal approach. These corridors identify areas where new transmission is needed to alleviate congestion and costs to ratepayers, potentially streamlining approval processes for lines within designated corridors.

Whether these federal initiatives will substantially ease the land aggregation challenge remains to be seen. State and local opposition to perceived federal overreach on land use issues remains strong in many regions.

Technology and Planning Tools That Help

Modern technology offers some solutions to traditional land aggregation challenges. Geographic Information Systems (GIS) allow developers to analyze thousands of potential routes, identifying paths that minimize impacts on sensitive properties, avoid areas likely to generate opposition, and reduce the total number of property owners requiring negotiation.

Advanced routing algorithms can factor in not just engineering considerations like terrain and distance, but also social factors like property values, land use types, and proximity to residences. This helps developers propose routes that are more likely to gain acceptance.

Visualization tools that show property owners what a transmission line will actually look like from their property, using accurate renderings and viewshed analysis, help ground conversations in reality rather than worst-case fears.

Online portals where property owners can access project information, submit questions, and track the status of negotiations with their property provide transparency and reduce the information asymmetry that often breeds distrust.

For organizations like Almighty Energy working on large-scale transmission projects, investing in these tools and the expertise to use them effectively is becoming less optional and more essential to project success.

What the Future Holds for Interstate Transmission Development

The need for long-distance transmission isn’t going away. Reliability was the primary driver of most (51 percent) new transmission lines over 2010-2020, with the proportion of transmission circuit-miles installed to meet reliability needs growing from 44 percent to 74 percent. As renewable energy deployment accelerates, the need for lines that can move power from where it’s generated to where it’s consumed will only grow.

Looking ahead, the number of proposals for new transmission lines is expected to increase. This means more projects will face the land aggregation challenges described here, making it increasingly important to apply lessons learned and improve processes.

The companies and developers that will succeed in this environment are those that approach land aggregation not as an afterthought once engineering is complete, but as a central part of project planning from day one. They’ll invest in community relationships, offer fair compensation, work transparently, and leverage technology to find routes that minimize conflicts.

For Almighty Energy and others in the transmission development space, the path forward requires balancing technical excellence with social and political savvy. The engineering challenges of building transmission lines are well understood. The human challenges of securing the land to build them remain the limiting factor for most projects.

FAQs

What is the typical timeline for aggregating land for a multi-state transmission line?

The timeline varies significantly by project, but most multi-state transmission lines take 10 to 20 years from initial planning to completion. Land aggregation itself typically requires 2 to 5 years once regulatory approvals are secured. The process includes identifying property owners, conducting appraisals, negotiating easements, and potentially pursuing eminent domain for properties where voluntary agreements can’t be reached.

How much compensation can landowners expect for transmission line easements?

Compensation is based on the difference between the property’s value before and after the easement. Factors include acreage directly impacted, restrictions on future land use, visual impacts, and damage to remaining property. Agricultural land might receive $10,000 to $50,000 per acre for easement rights, but values vary widely based on location, property type, and negotiation. Landowners who hire legal representation typically receive significantly more than initial offers.

Can utilities force landowners to sell through eminent domain?

Yes, utilities granted eminent domain authority by states can condemn property for transmission lines deemed to serve the public interest. But significant protections exist. Utilities must first demonstrate need, consider alternative routes, and provide fair compensation. They must give property owners time to seek legal advice and make written offers based on professional appraisals. Property owners can challenge both the necessity of the taking and the compensation amount in court.

Why do multi-state transmission projects face more challenges than single-state projects?

Multi-state projects must navigate different regulatory frameworks, approval processes, and standards in each state they cross. States in the middle of a transmission corridor may focus on local impacts without seeing proportional benefits, making approvals harder to obtain. Cost allocation disputes arise over who should pay when benefits and costs fall unevenly across states. Each additional state boundary adds complexity, delays, and potential points of opposition that can stall projects.

What rights do landowners retain after granting transmission line easements?

Landowners typically retain ownership and can continue most property uses that don’t interfere with line operation and maintenance. Permitted activities usually include farming, ranching, grazing, and installing fences. Restrictions typically prevent building structures under lines, planting tall-growing trees within the right-of-way, and activities that could damage line infrastructure. The specific terms are negotiable, so landowners should carefully review easement agreements before signing to ensure they protect their interests.